Gateway Keeping: The Third Circuit Joins the Sixth in Holding that Courts get to Decide whether Parties Consented to Class Arbitration

August 28th, 2014 American Arbitration Association, Appellate Practice, Arbitrability, Arbitration Agreements, Arbitration as a Matter of Consent, Arbitration Practice and Procedure, Arbitration Provider Rules, Authority of Arbitrators, Awards, Class Action Arbitration, Class Action Waivers, Consent to Class Arbitration, Consolidation of Arbitration Proceedings, Drafting Arbitration Agreements, Existence of Arbitration Agreement, Judicial Review of Arbitration Awards, Practice and Procedure, Stay of Litigation, United States Court of Appeals for the Sixth Circuit, United States Court of Appeals for the Third Circuit, United States Supreme Court Comments Off on Gateway Keeping: The Third Circuit Joins the Sixth in Holding that Courts get to Decide whether Parties Consented to Class Arbitration

On June 10, 2013 the U.S. Supreme Court in Oxford Health Plans LLC v. Sutter, 133 S. Ct. 2064 (2013) considered whether an arbitrator exceeded his powers under Federal Arbitration Act (“FAA”) Section 10(a)(4) by finding that a fairly run-of-the-mill arbitration agreement authorized class arbitration. Applying the deferential, manifest-disregard-of-the-agreement outcome-review standard authorized by FAA Section 10(a)(4), the Court upheld an arbitrator’s determination that an arbitration agreement authorized class arbitration because the arbitrator had, at least arguably, interpreted the arbitration agreement, albeit in a highly creative and doubtful way. (See Loree Reins. & Arb. L. Forum posts here, here, here & here.)

In a footnote, the Court explained that it “would face a different issue if Oxford had argued below that the availability of class arbitration is a so-called ‘question of arbitrability.’” 133 S. Ct. at 2068 n.2. The Court said that Stolt-Nielsen, S.A. v. AnimalFeeds Int’l Corp., 559 U.S. 662, 680 (2010), “made clear that this Court has not yet decided” whether class-arbitration-consent presents a question of arbitrability. But “Oxford agreed that the arbitrator should determine whether its contract with Sutter authorized class procedures[,]” and “Oxford submitted that issue to arbitrator not once, but twice—and the second time after Stolt-Nielsen flagged that it might be a question of arbitrability.” 133 S. Ct. at 2068 n.2. (emphasis added)

Had Oxford opted to request the Supreme Court to determine whether class- arbitration consent presented a question of arbitrability, and had the Court determined that it was such a question, then the Court would have determined independently—that is, without deferring to the arbitrator’s decision—whether the parties consented to class arbitration. See BG Group plc v. Republic of Argentina, No. 12-138, slip op. at 6 (U.S. March 5, 2014); First Options of Chicago, Inc. v. Kaplan, 543 U.S. 938, 942 (1995). And we doubt that a majority of the Supreme Court would have upheld the Oxford award had it reviewed the class-arbitration-consent determination de novo. See, e.g., Oxford, 133 S. Ct. at 2071 (Alito, J., concurring) (“If we were reviewing the arbitrator’s interpretation of the contract de novo, we would have little trouble concluding that he improperly inferred “[a]n implicit agreement to authorize class-action arbitration … from the fact of the parties’ agreement to arbitrate.”) (quoting Stolt-Nielsen, 559 U.S. at 685).  

Those who have been tracking developments in class and consolidated arbitration since the turn of this century no doubt recall that, after a plurality of the Court determined in Green Tree Financial Corp. v. Bazzle, 539 U.S. 444, 452-53 (2003), that a class-arbitration-consent-related dispute did not present a question of arbitrability, but merely a procedural question, parties began to submit routinely and unreservedly class-arbitration-consent questions to arbitration.

But after Stolt-Nielsen, and, no doubt with renewed vigor after Oxford, class arbitration opponents began to argue that class-arbitration-consent presented a question of arbitrability for the Court to decide. And U.S. Circuit Courts of Appeals are beginning to rule on those challenges.

The first one to do so was the U.S. Court of Appeals for the Sixth Circuit in Reed Elsevier, Inc. v. Crockett, 734 F.3d 594 (6th Cir. 2013), where the Court in November 2013 held “that the question whether an arbitration agreement permits classwide arbitration is a gateway matter, which is reserved for judicial determination unless the parties clearly and unmistakably provide otherwise.” 734 F.2d at 599 (quotation and citation omitted).

The second, and most recent Circuit Court of Appeals to rule on the issue, was the U.S. Court of Appeals for the Third Circuit in Opalinski v. Robert Half Int’l Inc., ___ F.3d ___, No. 12-4444, slip op. (3rd Cir. July 30, 2014), which on July 30, 2014 “join[ed] the Sixth Circuit Court of Appeals in holding that.  .  .  “the availability of” class arbitration “is a substantive gateway question rather than a procedural one[,]” and thus “is a question of arbitrability.” Slip op. at 15, 16-17.  The Court’s decision turned on “the critical differences between individual and class arbitration and the significant consequences of that determination for both [a] whose claims are subject to arbitration[;] and [b] the type of controversy to be arbitrated.” Slip op. at 15 (emphasis added). Where, as in Opalinski, the arbitration agreement did not “mention” class arbitration, the Court “believ[ed] the parties would have expected a court, not an arbitrator, to determine the availability of class arbitration[,]” and that was “especially so given the critical differences between individual and class arbitration and the significant consequences” of the class-arbitration-consent determination as respects “whose claims are subject to arbitration and the type of controversy to be arbitrated.” slip op. at 16-17.

The Third Circuit’s Opalinski decision, like the Sixth Circuit’s in Reed Elsevier, is well reasoned and reaches the conclusion we likewise think is required by the Supreme Court’s long-line of arbitrability jurisprudence, and by its post-Bazzle class-arbitration cases, beginning with Stolt-Nielsen. We suspect that other circuits will, for largely the same reasons, that class-arbitration-consent presents a question of arbitrability.

Let’s have a look at what transpired in Opalinski.  .  .  . Continue Reading »

Faithful to the “First Principle” of Arbitration Law, the Texas Supreme Court Shores up the “Cornerstone of the Arbitral Process”

August 5th, 2014 American Arbitration Association, Appellate Practice, Arbitration Agreements, Arbitration as a Matter of Consent, Arbitration Practice and Procedure, Arbitration Provider Rules, Arbitrator Selection and Qualification Provisions, Authority of Arbitrators, Awards, Confirmation of Awards, Contract Interpretation, Drafting Arbitration Agreements, Grounds for Vacatur, Judicial Review of Arbitration Awards, Party-Appointed Arbitrators, Practice and Procedure, State Courts, Texas Supreme Court Comments Off on Faithful to the “First Principle” of Arbitration Law, the Texas Supreme Court Shores up the “Cornerstone of the Arbitral Process”

Introduction  

Anyone versed in arbitration-law basics knows that “arbitration is a matter of consent, not coercion.” Stolt-Nielsen, S.A. v. AnimalFeeds Int’l Corp., 559 U.S. 662, 678-80 (2010) (citation and quotations omitted). That is the “first principle” of arbitration law (the “First Principle”) set forth in the Steelworkers’ Trilogy.[1] See, e.g., Granite Rock Co. v. International Brotherhood of Teamsters, 561 U.S. 287, 295 & n.7, 294 n.6 (2010); AT&T Technologies, Inc. v. Communications Workers, 475 U. S. 643, 648 (1986).

The First Principle is integrally intertwined with “the central or primary purpose of the [Federal Arbitration Act (“FAA”)][,]” which is “to ensure that  private agreements to arbitrate are enforced according to their terms.” Stolt-Nielsen, 559 U.S. at 679 (citations and quotations omitted). To “enforce” an arbitration agreement “courts and arbitrators must give effect to the contractual rights and expectations of the parties.” Id. When courts do not give effect to the parties’ contractual rights and expectations, they violate the First Principle.

Courts and arbitrators are supposed to apply the First Principle faithfully and rigorously whenever  they interpret or apply material arbitration-agreement-terms, and in “doing so [they] must  not lose sight of the purpose of the exercise: to give effect to the intent of the parties.” See Stolt-Nielsen, 559 U.S. at 679-81. And if that admonition applies with special force in any particular context, it would be in the interpretation and enforcement of arbitrator selection and qualification provisions.

Arbitrator selection provisions are what Circuit Court Judge Richard A. Posner once dubbed the “cornerstone” of the parties’ agreement: “Selection of the decision maker by or with the consent of the parties is the cornerstone of the arbitral process.” Lefkovitz v. Wagner, 395 F.3d 773, 780 (2005) (Posner, J.); see, e.g., 9 U.S.C. § 5 (“If in the agreement provision be made for a method of naming or appointing an arbitrator or arbitrators or an umpire, such method shall be followed.  .  .  .”); Convention on the Recognition and Enforcement of Foreign Arbitral Awards, Art. V(1)(d), June 10, 1958, 21 U.S.T. 2519, T.I.A.S. No. 6997 (a/k/a the “New York Convention”) (implemented by 9 U.S.C. §§ 201, et. seq.) (award subject to challenge where “[t]he composition of the arbitral authority or the arbitral procedure was not in accordance with the agreement of the parties”); Stolt-Nielsen, 559 U.S. at 668, 670 (one of the FAA’s “rules of fundamental importance” is parties “may choose who will resolve specific disputes”) (emphasis added; citations omitted); Encyclopaedia Universalis S.A. v. Encyclopaedia Brittanica, Inc., 403 F.3d 85, 91-92 (2d Cir. 2005) (vacating award by panel not convened in accordance with parties’ agreement); Cargill Rice, Inc. v. Empresa Nicaraguense Dealimentos Basicos, 25 F.3d 223, 226 (4th Cir. 1994) (same); Avis Rent A Car Sys., Inc. v. Garage Employees Union, 791 F.2d 22, 25 (2d Cir. 1986) (same).

Americo Life, Inc. v. Myer

On June 20, 2014, a divided Texas Supreme Court in Americo Life, Inc. v. Myer, ___ S.W.3d __, No. 12-0739, slip op. (Tex. June 20, 2014), adhered to and correctly applied the First Principle by holding that an arbitration award had to be vacated because it was made by a panel not constituted according to the parties’ agreement.  Five Justices of the nine-member Court determined that the parties had agreed that party-appointed arbitrators need not be impartial, only independent. Because the American Arbitration Association (the “AAA”) had, contrary to the parties’ agreement, disqualified the challenging party’s first-choice arbitrator on partiality grounds, the panel that rendered the award was not properly constituted and thus exceeded its powers. See Slip op. at 10. Continue Reading »

Re Colorado Energy Management, LLC v. Lea Power Partners, LLC: Another Appellate Division holds Construction Arbitration Award should be Vacated, but this time for Good Reason

May 10th, 2014 American Arbitration Association, Appellate Practice, Arbitrability, Arbitration Practice and Procedure, Arbitrator Vacancy, Authority of Arbitrators, Awards, Construction Industry Arbitration, Functus Officio, Grounds for Vacatur, Judicial Review of Arbitration Awards, New York State Courts, Practice and Procedure, State Arbitration Law, State Arbitration Statutes, State Courts Comments Off on Re Colorado Energy Management, LLC v. Lea Power Partners, LLC: Another Appellate Division holds Construction Arbitration Award should be Vacated, but this time for Good Reason

Introduction

In our recent post on the Merion Construction case (here), we were pretty critical of New Jersey’s Superior Court, Appellate Division, for reversing a trial court decision confirming a modified arbitration award, finding it should have been vacated and the original award confirmed. Today’s post takes a brief look at a decision by another state’s Appellate Division—New York’s Supreme Court, Appellate Division, First Department—which held that another construction-industry award should be vacated.

In Merion Construction the New Jersey Appellate Division thought the arbitrator had no authority to correct his award to reflect the rulings he intended to make on two issues the parties had submitted to him. Re Colorado Management, LLC v. Lea Power Partners, LLC , ___ A.D.3d ___, ___, 2014 N.Y. Slip Op. 01253 at 1-3 (1st Dep’t Feb. 20, 2014), held that a final arbitration award had to be vacated because the arbitrator had no authority to rule upon an issue that was not presented to him in light of the parties’ submissions and a ruling made in the same proceeding by a predecessor arbitrator.

While Merion Construction got an “F,” Colorado Management gets at least an “A-,” and perhaps even an “A.” Continue Reading »

The United States Supreme Court Adopts Severability Analysis in Rent-A-Center v. Jackson

June 21st, 2010 Arbitrability, Arbitration Practice and Procedure, Authority of Arbitrators, Class Action Arbitration, Class Action Waivers, Practice and Procedure, Unconscionability, United States Court of Appeals for the Ninth Circuit, United States Supreme Court Comments Off on The United States Supreme Court Adopts Severability Analysis in Rent-A-Center v. Jackson

Yesterday the United States Supreme Court decided Rent-A-Center West v. Jackson, ___ U.S. ___, slip op. (June 21, 2010).  Rent-A-Center raised the question whether “a district court may decide a claim that an arbitration agreement is unconscionable, where the agreement explicitly assigns that decision to the arbitrator.”  The United States Court of Appeals for the Ninth Circuit had said “yes,” but the Supreme Court said “no.”

In a 5-4 opinion by Associate Justice Antonin Scalia, joined in by Chief Justice John G. Roberts, Jr. and Associate Justices Anthony M. Kennedy, Clarence Thomas and Samuel A. Alito, Jr , the Court held that the employee had to arbitrate its claim that certain provisions of an arbitration agreement were allegedly unconscionable because the parties clearly and unmistakably agreed to arbitrate arbitrability questions, and the employee did not specifically claim that that agreement was unconscionable.  The Court said that the parties’ clear and unmistakable agreement to arbitrate arbitrability was, as a matter of federal law, severable from the other provisions of the arbitration agreement, including the ones the employee said were unconscionable.  

Prior to the decision we had advocated in the Forum (here and here), and in our cover story published in the March 2010 issue of Alternatives to the High Cost of  Litigation (blogged here), that the Court should resolve the case in favor of Rent-A-Center using a severability analysis of sorts derived from Buckeye Check Cashing v. Cardegna, 546 U.S. ___ (2006) and Prima Paint Corp. v. Flood & Conklin Mfg. Co., 388 U.S. 395 (1967).   And that’s exactly what happened, even though neither side advocated or addressed the severability argument before the Court, a point made by Associate Justice Stevens’ dissenting opinion, which was  joined in by Associate Justices Ruth Bader Ginsburg, Stephen G. Breyer and Sonia Sotomayor.  See Dissenting Op. at 1.  (The district court’s analysis, however, which was reversed by the Ninth Circuit, was, according to the Court, consistent with the Buckeye Check Cashing and Prima Paint severability principle.  See Slip op. at 9.)  Continue Reading »