main image

Archive for August, 2018

California Appeals Court Says Clause Construction Award is not Final Award Subject to Confirmation or Vacatur

August 29th, 2018 Arbitration as a Matter of Consent, Arbitration Practice and Procedure, Awards, California State Courts, Class Action Arbitration, Clause Construction Award, Confirmation of Awards Comments Off on California Appeals Court Says Clause Construction Award is not Final Award Subject to Confirmation or Vacatur

Introduction

Clause Construction Award 1

Clause Construction Award 1

We have discussed (here) what constitutes a final award under the Federal Arbitration Act, an issue that is important for a host of reasons, but is particularly so to any business faced with an adverse clause construction award. A clause construction award is an interim or partial final arbitration ruling that determines the threshold issue of whether the parties consented to class arbitration.

 

But not all arbitrations – even class arbitrations – are governed by the Federal Arbitration Act (“FAA”), and even when they are, parties may agree to procedural rules that are different from those of the FAA. See Preston v. Ferrer, 128 S.Ct. 978, 987-89 (2008); Volt Info. Sciences, Inc. v. Board of Trustees of Leland Stanford Jr. Univ.,  489 U.S. 468, 478-79 (1989). In Maplebear, Inc. v. Busick, ___ Cal. App.5th ___, slip op. (Cal. App., 1st Dist. August 21, 2018) (certified for publication), the parties agreed that  “the arbitration would be conducted by JAMS under its rules and procedures; the arbitrator would apply California substantive law; the arbitrator had no ‘power or authority to commit errors of law or legal reasoning’; and ‘[a]ny action to review the arbitration award for legal error or to have it confirmed, corrected or vacated’ would be decided under California law by ‘a California state court of competent jurisdiction.’” Slip op. at 2.

At issue in Maplebear was whether the California courts had jurisdiction to vacate a partial final Clause Construction Award, which concluded that the parties had consented to class arbitration. The California Appeals Court said “no,” which means that—unless the California Supreme Court (or the U.S. Supreme Court) hears an appeal and says otherwise—the parties have to endure through an entire class arbitration procedure before there is any judicial review of the Clause Construction Award. (Whether or not review by the California Supreme Court or the U.S. Supreme Court is even possible given the procedural posture of this case is outside the scope of this post.)

 

An Unfair Burden on the Clause Construction Award Challenger?

Clause Construction Award 2

Clause Construction Award 2

Consider the burden the decision imposes on the class-arbitration opponent. According to the majority opinion in Concepcion, then fairly current American Arbitration Association statistics showed that: (a) “[a]s of September 2009, the AAA had opened 283 class arbitrations[;]” (b) “[o]f those, 121 remained active, and 162 had been settled, withdrawn, or dismissed[;]” (c) “[n]ot a single one, however, had resulted in a final award on the merits[;]” and (d) “[f]or those cases that were no longer active, the median time from filing to settlement, withdrawal, or dismissal—not judgment on the merits—was 583 days, and the mean was 630 days.” AT&T Mobility LLC v. Concepcion, 131 S.Ct. 1740, 1751 (2011).

Clause Construction Award 4

Clause Construction Award 4

While we have not researched whether more recent statistics tell a different story, it seems quite likely that the Court’s decision on finality means that the class arbitration opponent will have to spend an awful lot of time and money before the issue of class arbitration consent is reviewed by a court, assuming it is ever reviewed.

 

Continue Reading »

Class-Arbitration-Consent: The Eleventh Circuit Creates Circuit Split by Ruling that Incorporation of AAA Rules is Clear and Unmistakable Consent to Arbitrate Class-Arbitration-Consent Questions

August 24th, 2018 Arbitrability, Arbitration Agreements, Arbitration as a Matter of Consent, Arbitration Practice and Procedure, Authority of Arbitrators, Class Action Arbitration, Class Action Waivers, Consent to Class Arbitration, FAA Preemption of State Law, United States Court of Appeals for the Eleventh Circuit, United States Supreme Court Comments Off on Class-Arbitration-Consent: The Eleventh Circuit Creates Circuit Split by Ruling that Incorporation of AAA Rules is Clear and Unmistakable Consent to Arbitrate Class-Arbitration-Consent Questions

Introduction

Class-Arbitration-Consent 1

Class-Arbitration-Consent 1

In prior posts we’ve discussed how footnote 2 of the U.S. Supreme Court’s decision in Oxford Health Plans LLC v. Sutter, 133 S. Ct. 2064, 2072 n.2 (2013) said it was an open issue whether class-arbitration-consent presented a question of arbitrability, and how certain U.S. Circuit Courts of Appeals have, subsequent to Oxford, held that consent-to-class-arbitration presents a question of arbitrability, which is ordinarily for the court to decide. (See, e.g., here.)

We have also discussed how, under First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938, 942-46 (1995), even though questions of arbitrability are ordinarily for the court to decide, parties may clearly and unmistakably agree to submit questions of arbitrability to the arbitrators. In Rent-A-Center, West, Inc. v. Jackson, 130 S. Ct. 2772, 2777 (2010), the Supreme Court of the United States referred to such agreements as “delegation provisions.” Id.

Class-Arbitration-Consent 2

Class-Arbitration-Consent 2

In Spirit Airlines, Inc. v. Maizes, ___ F.3d ___, slip op. (11th Cir. August 15, 2018), the United States Court of Appeals for the Eleventh Circuit addressed a question that called in to play these two related concepts: “whether the [parties’] agreement’s choice of American Arbitration Association rules, standing alone, is clear and unmistakable evidence that [the parties] intended that the arbitrator decide” the consent-to-class-arbitration question. Slip op. at 2. The Court said the answer to that question was “yes.”

Continue Reading »

Eighth Circuit: Arbitrator did not Disregard Parties’ Missouri Choice-of-Law Provision

August 19th, 2018 Arbitration Practice and Procedure, Authority of Arbitrators, Awards, Choice-of-Law Provisions, Exceeding Powers, Judicial Review of Arbitration Awards, Manifest Disregard of the Agreement, Manifest Disregard of the Law, United States Court of Appeals for the Eighth Circuit Comments Off on Eighth Circuit: Arbitrator did not Disregard Parties’ Missouri Choice-of-Law Provision

Introduction

Choice-of-Law Provision 1

Choice-of-Law Provision 1

A choice-of-law provision is as much a part of a parties’ contract as any other, and an arbitrator might manifiestly disregard the parties’ contractual choice-of-law, which might provide grounds for vacating the award under Section 10(a)(4) of the Federal Arbitration Act (“FAA”). But, as well-illustrated by the U.S. Court of Appeals for the Eigth Circuit’s decision in Beumer Corp. v. ProEnergy Servs., LLC, ___ F.3d ____, slip op. (8th Cir. August 8, 2018), the circumstances that might justify such a decision would be very unusual, to say the least.

Beumer Corp. v. ProEnergy Servs., LLC

Choice-of-Law Provision 2

Choice-of-Law Provision 2

Owner and Contractor had a construction contract that contained an arbitration agreement, limitation-of-liability, provision, and a Missouri choice-of-law clause. The Owner complained that the Contractor’s work was deficient and, accordingly, no payment was due. The Contractor commenced arbitration for the amount due under the contract and the Owner counterclaimed for damages.

The parties disputed the scope and enforceability of their contract’s limitation of liability provision, which stated:

Notwithstanding any of the foregoing or any other term in this Contract, the total liability of Contractor for any loss, indemnity, damage or delay of any kind will not under any circumstances exceed 100% of the Contract Sum.

The contract contained a broad Missouri choice-of-law clause, and provided that a prevailing party could collect its attorney’s fees.

The Award

Choice-of-Law Provision 3

Choice-of-Law Provision 3

The Arbitrator ruled that the clause was enforceable, that the Contract Sum (i.e., the liability cap) was $699,702.39., and that the terms “loss, indemnity, damage or delay of any kind” did not include the prevailing party’s contractual right to attorney fees. The Arbitrator thus awarded Beumer: (a) $699,702.39 in damages; (b) $191,680.14 in pre-judgment interest; (c) post-judgment interest at 9%; and (d) $916,027.90 in attorney’s fees and expenses.

On its motion to vacate the Award the Contractor did not dispute that the Arbitrator “arguably construed” the limitation of liability clause, but contended that the Arbitrator exceeded its powers by “disregarding” the Missouri choice-of-law clause, because: (a) the Arbitrator relied on caselaw from four jurisdictions outside of Missouri to support his construction of the limitation of liability provision as exclusive of costs and attorney fees, and did not cite any Missouri decisions on this construction question; and (b) the Contractor claimed that the Missouri cases required a cost-inclusive interpretation of the clause, not a cost-plus one.

The Arbitrator did not Disregard the Choice-of-Law Provision

Choice-of-Law Provision 4

Choice-of-Law Provision 4

Did the Arbitrator exceed his powers by ruling that the limitation of liability clause did not limit liability for contractual attorney fees? The Eighth Circuit, in a well-reasoned decision, said the answer was “no.” Continue Reading »

Appellate Division, Fourth Department Vacates Imperfectly Executed Arbitration Award

August 15th, 2018 Authority of Arbitrators, Awards, Exceeding Powers, Imperfectly Executed Award or Powers, Labor Arbitration, New York State Courts Comments Off on Appellate Division, Fourth Department Vacates Imperfectly Executed Arbitration Award
Imperfectly Executed 1

Imperfectly Executed 1

New York Civil Practice Law & Rules (“CPLR”) Section 7511(b)(1)(iii) provides that an arbitration award “shall be vacated” where the arbitrator “so imperfectly executed [the award] that a final and definite award upon the subject matter submitted was not made” CPLR 7511(b)(1)(iii). The Federal Arbitration Act similarly authorizes vacatur “where the arbitrators…so imperfectly executed [their powers] that a mutual, final, and definite award upon the subject matter submitted was not made.” 9 U.S.C. § 10(a)(4).

In Professional, Clerical, Tech. Emps. Ass’n v. Board of Ed. for Buffalo City School Dist., ___ A.D.3d ___, 2018 N.Y. Slip Op. 04128, at *1 (4th Dep’t June 8, 2018), the New York Supreme Court, Appellate Division, Fourth Department, held that the trial court erred by confirming a labor arbitration award that did not adequately explain the basis for the compensation to be awarded or how it should be calculated. Continue Reading »

The Fourth Circuit: What Constitutes a Final Award and Who Makes the Call?

August 3rd, 2018 Appellate Practice, Arbitrability, Arbitration Practice and Procedure, Authority of Arbitrators, Awards, Confirmation of Awards, Exceeding Powers, Federal Arbitration Act Enforcement Litigation Procedure, Grounds for Vacatur, Judicial Review of Arbitration Awards, Manifest Disregard of the Agreement, Manifest Disregard of the Law, United States Court of Appeals for the Fourth Circuit 1 Comment »
Final Award 2 - yay-15399450

Final Award 2

What constitutes a “final arbitration award” for purposes of the Federal Arbitration Act is important because it bears on whether an award can be confirmed, vacated, or modified under Sections 9, 10, or 11 of the Federal Arbitration Act (the “FAA”). We addressed the basics concerning final awards in a 2009 post, here.

In Northfolk Southern Railway Co. v. Sprint Communications Co., L.P., 883 F.3d 417 (4th Cir. 2018), the U.S. Court of Appeals for the Fourth Circuit was faced with the question whether an award (the “Appraisal Award”), convened under an agreement’s appraisal clause, and issued by three appraisers, was a final arbitration award under the FAA. The unusual procedural posture of the case raised an additional, related question: whether under the FAA an arbitration panel, convened under the arbitration provision of the parties’ agreement, had the authority to declare the Appraisal Award to be a final award. That question matters, for if an arbitration panel has that power, then its decision concerning finality is subject only to the very highly deferential review permitted by Section 10 of the FAA. See First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938, 942-43 (1995); Oxford Health Plans LLC v. Sutter, 133 S. Ct.  2064, 2068-69 (2013).

Concededly with the benefit of 20/20 hindsight, we wonder whether a different litigation and appellate strategy might have yielded a different outcome. The Court held that the Appraisal Award was not final, and remanded the matter back to the appraisers. But the Court did not, for the reasons set forth below, definitively answer the “who” question. The Court’s decision that the Appraisal Award was not final was unquestionably correct if one considers from a purely objective standpoint, without deference to the Arbitration Award, which declared that the Award was final.  But the correct outcome would be considerably less certain had the Railroad sought confirmation of the Arbitration Award and urged the Court to accord deference to the arbitrators who made it.

Background: Northfolk Southern Railway Co. v. Sprint Communications Co., L.P., 883 F.3d 417 (4th Cir. 2018)

Final Award 1 - yay-1618918-digital

Final Award 1

The dispute between Northfolk Southern Railway Co. (the “Railroad” or the “Appraisal Award Defending Party”) and Sprint Communications Co., L.P. (the “Carrier” or the “Appraisal Award Challenging Party”) arose out of a 25-year-term 1987 licensing agreement (the “Agreement”) under which the Carrier’s predecessor licensed from the Railroad’s predecessor the right to use for fiber-optics-cable purposes certain parts of the Railroad’s rights of way. The Carrier renewed that Agreement for an additional 25-year term (the “renewed Agreement term”), and a dispute arose about the renewal price. Continue Reading »