main image

Posts Tagged ‘fraud in arbitration’

Can a Party Obtain Post-Judgment Relief from a Confirmed Arbitration Award Procured by Fraud?

May 26th, 2015 Arbitration Practice and Procedure, Arbitration Risks, Asbestos-Related Claims, Bad Faith, Confirmation of Awards, Corruption or Undue Means, Definition of Occurrence, Federal Courts, Federal Rules of Civil Procedure, Final Awards, Grounds for Vacatur, United States Court of Appeals for the Second Circuit, United States District Court for the Southern District of New York Comments Off on Can a Party Obtain Post-Judgment Relief from a Confirmed Arbitration Award Procured by Fraud?

Introduction

Relief from an Arbitration Award Procured by Fraud

yay-14955744-digital

Section 10(a)(1) of the Federal Arbitration Act authorizes Courts to vacate arbitration awards that were “procured by fraud, corruption or undue means.”  9 U.S.C. § 10(a)(1). (For a discussion of Section 10(a)(1), see L. Reins. & Arb. Law Forum post here.) But a motion to vacate an arbitration award procured by fraud (or otherwise) is subject to a strict three-month deadline, and Section 10, unlike certain of its state-law counterparts, does not provide for tolling of the three-month deadline on the ground the challenging party did not know or have reason to know it had grounds to allege the arbitration award was procured by fraud. Compare 9 U.S.C. § 10(a)(1) with 2000 Revised Uniform Arbitration Act § 23(b) (Uniform Law Comm’n 2000) (If “the [movant] alleges that the award was procured by corruption, fraud, or other undue means, [then, in that].  .  .   case the [motion] must be made within 90 days after the ground is known or by the exercise of reasonable care would have been known by the [movant].”);  1955 Uniform Arbitration Act § 12(b) (Uniform Law Comm’n 1955) ( “[I]f predicated upon corruption, fraud or other undue means, [the motion to vacate] shall be made within ninety days after such grounds are known or should have been known.”).

Once an award has been confirmed, it has the same force and effect as any other judgment of the court. See 9 U.S.C. § 13. Federal Rule Civ. P. 60(b) provides that “[o]n motion and just terms, the court may relieve a party or its legal representative from a final judgment, order, or
proceeding for the following reasons:.  .  .  (3) fraud (whether previously called intrinsic or extrinsic), misrepresentation, or misconduct by an opposing party.  .  .  .” Fed. R. Civ. P. 60(c) provides that “[a] motion under Rule 60(b) must be made within a reasonable time—and for reasons (1), (2), and (3) [i.e., fraud, misrepresentation or misconduct] no more than a year after the entry of the judgment or order or the date of the proceeding.” Fed. R. Civ. P. 60(c).

So can a challenging party obtain relief from a confirmation judgment if: (a) an award-challenging party contends the Court entered judgment oin an arbitration award procured by fraud; (b) by extension, the judgment confirming the award was itself procured by fraud; (c) the award-challenging party did not know or have reason to know it was at the wrong end of an arbitration award procured by fraud until after the three-month statute of limitations for vacating an award had elapsed; and (d) the award-challenging party makes a timely motion for post-judgment relief under Fed. R. Civ. P. 60(b)? According to a district court judge of the U.S. District Court for the Southern District of New York, the answer is “no.”

 

Arrowood Indem. Co. v. Equitas Insurance Ltd., No. 13-cv-7680 (DLC), slip op. (S.D.N.Y. May 14, 2015)

No Post-Judgment Relief from Arbitration Award Procured by Fraud (Alleged or Otherwise)

Background

yay-677177

Arrowood arose out of an excess-of-loss treaty Arrowood’s predecessor(s) in interest had entered into with Underwriters at Lloyd’s in the 1960s. The terms of the treaty were apparently part of, or incorporated into, a “Global Slip,” which the Court, without much elaboration, described as “a complex contractual  reinsurance program.” The Global Slip was first negotiated in 1966 and effective January 1, 1967 through December 31, 1968. It was apparently renewed a number of times thereafter, though the court does not say for what period or periods. The renewal agreements were “substantially similar” although they “contain[ed] new contractual language.” Slip op. at 2.

The Global Slip covered (apparently among other things) losses in excess of $1 million incurred under Arrowood’s casualty insurance policies under three different types of coverage. At issue was “Common Cause Coverage,” which covered losses arising out of an “occurrences” during the contract term, provided the occurrence or occurrences were the “probable common cause or causes” of more than one claim under the policies. The Global Slip also contained a “First Advised” clause, which said that “this Contract does not cover any claim or claims arising from a common cause, which are not first advised during the period of this Contract.”

yay-1299629-digitalLike so many other liability insurers, Arrowood began receiving, adjusting and settling asbestos bodily injury claims beginning in the 1980s. Underwriters at Lloyd’s London insisted that Arrowood present its asbestos reinsurance claims on a per claimant per exposure-year basis, absorbing one $1 million retention each year against the total asbestos claim liabilities allocated to that year under the Underwriters’ per claimant per exposure-year allocation methodology.

In 2008 Arrowood, after reviewing the contract language, stopped using exclusively the Underwriters-prescribed asbestos personal-injury claim reinsurance allocation methodology, which it had followed for almost 25 years, and began presenting a number of claims under the Common Cause Coverage provision of the Global Slip . Because those claims were not, “first advised” in the years 1967 or 1968, the Underwriters denied them.

The Arbitration and Confirmation Proceedings

One of the parties demanded arbitration in October 2010, and a tripartite panel was appointed. The Underwriters argued, among other things, that: (a) the parties’s 25-year course of dealing evidenced a binding agreement on how asbestos claims would be presented to the Underwriters; (b) some claims fell exclusively under employer’s liability coverage; and (c) Common Cause Coverage  did not apply because the requirements of the First Advised Clause were not satisfied. Continue Reading »