Unlawful Limitations Period Provision Renders Arbitration Agreement Unenforceable Says South Carolina Supreme Court

January 2nd, 2025 Contract Defenses, Enforcing Arbitration Agreements, FAA Chapter 1, FAA Section 2, FAA Section 4, Federal Arbitration Act Enforcement Litigation Procedure, Federal Arbitration Act Section 2, Federal Arbitration Act Section 4, Petition to Compel Arbitration, Policy, Practice and Procedure, Pre-Award Federal Arbitration Act Litigation, Public Policy, Section 2, Section 4, Severability, South Carolina Supreme Court, State Courts No Comments »

Severability of Limitations Provision: Introduction

Limitations

One defense to a motion to compel arbitration is that the arbitration agreement on which the movant relies is, as a matter of arbitration-neutral state law, void or unenforceable on public policy grounds. (See, e.g., here.) But if only one term or provision of an arbitration agreement is unenforceable on public policy grounds, can that offending provision simply be removed from the contract and the rest of the arbitration agreement enforced?

In Huskins v. Mungo Homes, LLC, No. 28245, slip op. (S.C. Sup. Ct. December 11, 2024), the South Carolina Supreme Court said the answer depends principally on the intent of the parties. And as respects the adhesive, “take-it-or-leave-it” home sale contract before it, the Court said the answer was no.

By statute South Carolina prohibits and deems void contractual provisions that purport to shorten the statute of limitations. S.C. Code Ann. § 15-3-140 (2005).  In Mungo Homes, the defendant sold the plaintiff a new home, the contract of sale for which contained an arbitration agreement that said: “Each and every demand for arbitration shall be made within ninety (90) days after the claim, dispute or other matter in question has arisen, except that any claim, dispute or matter in question not asserted within said time periods shall be deemed waived and forever barred.” Slip op. at 2 (quotation omitted). The parties agreed that provision violated Section 15-3-140.

The question before South Carolina’s highest court was whether the provision could be severed from the contract, leaving intact the rest of the arbitration agreement, and the contract containing it (the “container contract”), or whether that unlawful provision rendered invalid and unenforceable the entire arbitration agreement. In Huskins the Court held that the limitations period provision could not be severed and the arbitration agreement was accordingly unenforceable on public policy grounds. The container contract was not affected by the Court’s decision. Slip op. at 6.

Discussion

Severability of Limitations Provision: Party Intent and Relevance of not Including a Severability Clause in the Agreement

The Court said “[t]he only question we are left with is whether we should sever the illegal term and let the remainder of the arbitration agreement stand.” Slip op. at 3. The touchstone for answering that question was party intent: “whether an agreement can be modified so its remaining provisions survive [generally] depends upon what the parties intended.” Slip op. at 2.

The Court observed that the parties did not include in their contract a severability provision and the contract otherwise did not suggest the parties intended the arbitration agreement to survive if any part of it, including the limitations provision, was deemed void. Slip op. at 2.

The Court explained that the absence of a severability clause, in and of itself, may be grounds for not severing an unenforceable clause from a contract. For courts are not supposed to “rewrite contracts” but (subject to certain exceptions) enforce them according to their terms. Slip op. at 2.

But the Court decided not to rest its decision solely on the parties’ decision not to include a severability clause in their contract. The Court explained that, in the absence of a severability clause, Courts are reluctant to impose severability on the parties. Slip op. at 2-3. Yet “devotion to that principle[,]” said the Court, “can work a cost to other interests. It can exact a needless forfeiture or cause unjust enrichment, tossing out the essence of a bargained for exchange over a trivial technicality.” Slip op. at 3 (citation omitted).

Severability of the Limitations Provision: Common Law, South Carolina Law, and the Restatement (Second) of Contracts

The Court briefly discussed pertinent English common law, and U.S. and South Carolina precedent on the severability issue, explaining how courts have “stricken illegal parts from contracts and upheld the legal parts, as long as the central purpose of the parties’ agreement did not depend on the illegal part.” Slip op at 3. South Carolina, said the Court, “followed this main current and interpreted contracts as severable if consistent with the parties’ intent.” Slip op. at 3 (citations omitted).

The Restatement (Second) of Contracts, said the Court, “takes the further view that if only part of a contract term is unenforceable on the grounds of public policy, a court may enforce the rest of the term as long as 1) ‘the performance as to which the agreement is unenforceable is not an essential part of the agreed exchange’ and 2) the party seeking to enforce the term ‘obtained it in good faith and in accordance with reasonable standards of fair dealing.’” Slip op. at 3-4 (quoting Restatement (Second) of Contracts § 184). Restatement (Second) Section 184’s comments, in turn, “emphasize that ‘a court will not aid a party who has taken advantage of his dominant bargaining power to extract from the other party a promise that is clearly so broad as to offend public policy by redrafting the agreement so as to make a part of the promise enforceable.’” Slip op. at 4 (quoting Restatement (Second) § 184, comment b).

No Question of Fact that the Parties did not Intend to Permit Severability of the Limitations Provision

The Court determined that, although party intent is often a question of fact, there were three reasons why there was no such question concerning party intent not to allow severability:

  1. The parties did not agree to a severability clause;
  2. The contract’s merger clause states that the “contract ‘embodies the entire agreement’ and that it can only ‘be amended or modified’ by a writing executed by both the Huskins and Mungo[;]” and
  3. Mungo conceded that the contract was an adhesion contract.

Slip op. at 4.

The Court found that the contract was offered on a “‘take it or leave it’” basis, drafted by Mungo, deemed nonnegotiable, and not editable by the Huskins. Slip op. at 4. “This forceful proof,” said the Court, “of Mungo’s intent that the contract could not be tinkered with convinces us we should not rewrite it now.” Slip op. at 4.

The Court further concluded that the illegal provision in the arbitration agreement was material because it would be outcome determinative of many disputes. Slip op. at 4. The Court viewed the provision not as a “mere ‘ancillary logistical concern’ of the arbitration agreement” but  “a brash push to accomplish through arbitration something our statutory law forbids.” Slip op. at 4 (citation omitted). Were the Court to to “lift[] out the clause, the legal statute limitations period (which in most cases allows claims to be filed within three years of their reasonable discovery) would drop in.” Slip op. at 4 (parenthetical material in original). That “would rewrite arbitration agreement to expand the statute of limitations by several orders of magnitude.” Slip op. at 4.

Arbitration, said the Court, is designed “to provide an alternative way to resolve disputes in a fair an efficient manner[,]” but “Mungo designed its arbitration provision not to streamline the resolution of disputes but to reduce their number” by greatly reducing the limitation period for bring those disputes. Slip op. at 4. The Court “conclud[ed] Mungo’s manipulative skirting of South Carolina public policy goes to the core of the arbitration agreement and weighs heavily against severance.” Slip op. at 4-5 (citations omitted)

The Court ruled that it would not save the arbitration agreement by severing the offending limitations provision, finding that because this was an “adhesion contract” it was “highly doubtful that the parties truly intended for severance to apply.” Slip op. at 5 (citation omitted). The contract was a consumer home-purchase agreement, triggering the “public policy concerns that [Damico v. Lennar Carolinas, LLC, 437 S.C. 596, 619-20 (2022)] eloquently addressed.” Slip op. at 5.

Permitting Severance would Provide a Perverse Incentive for Dominant Parties to Include in Adhesion Contracts Illegal Contract Provisions

“We have[,]” said the Court, been steadfast in protecting home buyers from unscrupulous and overreaching terms, and applying severance here would erode that laudable public policy.” Slip op. at 5 (citation omitted). Mungo wanted an “adhesion contract so its terms could not be varied and would stick[,]” and, now, “Mungo was stuck with its choice.” Slip op. at 5. Finding otherwise would ensure there was “no downside to throwing in blatantly illegal terms, betting they will go unchallenged or, at worst, that courts will throw them out and enforce the rest.” Slip op. at 5 (citations omitted).

The Court thus did not sever the offending contract provision and held that the arbitration agreement was therefore unenforceable. Slip op. at 6. It further found that the container contract contract was not affected by the Court’s ruling. Slip op. at 6.

Contacting the Author

If you have any questions about this article, arbitration, arbitration-law, arbitration-related litigation, then please contact Philip J. Loree Jr., at (516) 941-6094 or PJL1@LoreeLawFirm.com.

Philip J. Loree Jr. is principal of the Loree Law Firm, a New York attorney who focuses his practice on arbitration and associated litigation. A former BigLaw partner, he has nearly 35 years of experience representing a wide variety of corporate, other entity, and individual clients in matters arising under the Federal Arbitration Act, as well as in insurance- or reinsurance-related, and other, matters.

ATTORNEY ADVERTISING NOTICE: Prior results do not guarantee a similar outcome.

 Photo Acknowledgment

The photo featured in this post was licensed from Yay Images and is subject to copyright protection under applicable law.

 

Does the Presumption of Arbitrability Apply if a Contract Contains two Broad, Overlapping Forum Selection Clauses, one for Arbitration and one for Litigation?

June 7th, 2015 Arbitrability, Arbitration Agreements, Arbitration Practice and Procedure, Contract Interpretation, Contract Interpretation Rules, FAA Preemption of State Law, Federal Policy in Favor of Arbitration, Moses Cone Principle, Presumption of Arbitrability, Stay of Litigation, United States Court of Appeals for the Ninth Circuit Comments Off on Does the Presumption of Arbitrability Apply if a Contract Contains two Broad, Overlapping Forum Selection Clauses, one for Arbitration and one for Litigation?

Introduction

yay-4719842---Copy

 

Back in 1983 the U.S. Supreme Court, in the landmark decision Moses H. Cone Memorial Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24-25 (1983) (Brennan, J.), famously declared that “[t]he [Federal] Arbitration Act establishes that, as a matter of federal law, any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration, whether the problem at hand is the construction of the contract language itself or an allegation of waiver, delay, or a like defense to arbitrability.” Moses Cone thus established that there was a presumption in favor of arbitrability in cases governed by the Federal Arbitration Act, a conclusion that a number of other lower courts had previously reached, and which the Court had adopted about 23 years previously as a matter of federal labor law derived from Section 301 of the Labor Management Relations Act (sometimes referred to as the “Taft-Hartley Act”). See United Steel Workers of Am. v. Warrier & Gulf Nav. Co., 363 U.S. 574, 582-83 (1960) (Douglas, J.) (“An order to arbitrate the particular grievance should not be denied unless it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute. Doubts should be resolved in favor of coverage.”)

The presumption of arbitrability is not a talismanic solution to every arbitration-law related problem. In fact it is designed to address only questions about the scope of an arbitration agreement.

The presumption has two related components. First, when courts construe the scope provision of an arbitration agreement to determine what merits-related issues the parties agreed to arbitrate, the court resolves ambiguities in favor of arbitration.  See, e.g., Mastrobuono v. Shearson Lehman Hutton, Inc., 514 U.S. 52, 62 (1995). Second, it presumes that procedural issues arising out of arbitrable disputes, and contract-related defenses to arbitrability—that is, “allegation[s] of waiver, delay and like defenses to arbitrability[,]” are presumptively for the arbitrator. See Moses Cone, 460 U.S. at 24-25; Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 84 (2002).

Roughly ten days ago, in a post about U.S. Circuit Judge Richard A. Posner’s Sprint Spectrum decision, we wrote about how some judges have interpreted the presumption too expansively:

The federal policy in favor of arbitration has, at least arguably, been interpreted to apply more expansively than the U.S. Supreme Court likely intended. As a result, even though the U.S. Supreme Court has said many times that arbitration is supposed to be a “matter of contract,” or one of “consent not coercion,” an overly expansive interpretation of the policy has, at least in some cases, arguably resulted in arbitration agreements being placed on a considerably more advantaged footing than ordinary contracts. As we read it, Judge Posner’s comment in Roughneck raises the question whether this might have more to do with “limit[ing] judicial workloads” than a desire to enforce contracts as written and according to their terms.

(Read our Sprint Spectrum post here.)

With all the hoopla about the presumption of arbitrability, one would think it very difficult to find a case that didn’t apply the presumption of arbitrability in a situation where it was supposed to apply it. In general that’s probably true, but on June 2, 2015 the U.S. District Court for the Western District of Washington proved that truth is not a universal one.

In Scolari v. Elliot Rust Co., No. C15-5163 (BHS), slip op. (W.D. Wash. June 2, 2015) the court considered whether ambiguity created by apparently conflicting forum selections clauses: one arbitral and two judicial. While the Court’s reasoning indicated that it considered the issue before it one of contract interpretation—the resolution of ambiguity—it nevertheless held that the ambiguity had to be resolved against the drafter of the contract, which the district court thought Washington law required, rather than in favor of arbitration, which was what federal law required. While it apparently recognized that application of the presumption, rather than a state-law contra proferentem rule, would have required the court to stay the litigation, it nevertheless denied the requested stay of litigation, concluding that the issue before it concerned the enforceability of the arbitration agreement, rather than an interpretation of its scope.

The net effect of the ruling was for the district court to implicitly have found that a judicial forum selection clause trumped an arbitral one, simply because they overlapped in scope, and that accordingly the arbitral forum selection clause was not enforceable. There was no legal basis for such a finding and the district court cited none.

The seriousness of the error was compounded by the district court’s acknowledgement that the arbitration proponent had advanced a reasonable interpretation of the arbitration agreement and judicial forum selection clauses, which harmonized them, and would have allowed arbitration to proceed, with the district court staying its hand in the interim. Instead of adopting that interpretation, it said that the arbitration challenger’s interpretation was likewise “reasonable,” but the court did not say what the challenger’s interpretation was, and given the disposition of the case, we assume that the “interpretation” was that the parties must not have intended to include a concededly existing and valid arbitration agreement in their agreement. But that interpretation not only ignored the presumption of arbitrability, but the general rule of contract interpretation that one contract provision not be construed to negate another.

We do not know whether the arbitration proponent preserved the argument for appeal, but there was another ground for a stay of litigation in this case that would have bypassed the issue of the presumption of arbitrability. The arbitration agreement contained a delegation clause, which clearly and unmistakably required the parties to submit to arbitration all disputes about arbitrability. Because there was no dispute about the existence or validity of the delegation clause, the Court should have held that the resolution of the apparent conflict between arbitral and judicial forum selection clauses was a question for the arbitrators.

If the arbitration proponent decides to appeal the decision, we hope that the U.S. Court of Appeals for the Ninth Circuit will correct these errors without delay, so that the parties can arbitrate their disputes, which is, after all, what they agreed to do.

Background

yay-12775922-digitalScolari v. Elliot Rust Co., No. C15-5163 (BHS), slip op. (W.D. Wash. June 2, 2015), arose out of the purchase, sale, termination and buyback of an interest in a limited liability company. Effective January 1, 2013 the plaintiff (the “Buyer”) purchased a ten-percent ownership interest in  Elliot Rust Companies, LLC (the “LLC”), the purchase and sale of which was governed by a “Grant Agreement” executed by the parties “according to the terms of [an] Amended and Restated LLC Agreement of Elliot Rust Companies, LLC dated January 1, 2013.” Both agreements were apparently part of the same transaction and were entered into at or about the same time.

The Buyer and LLC were the only parties to the Grant Agreement, which provided that the Buyer would acquire its 10% interest “according to the terms of the terms of the Amended and Restated LLC Agreement of Elliot Rust Companies, LLC dated January 1, 2013

The Grant Agreement provided, among other things, that:

[Scolari] understands, acknowledges and agrees that, upon execution of this Grant Agreement and the joinder to the LLC Agreement, [Scolari] shall, without further action or deed, thereupon be bound by the LLC Agreement, as it may thereafter be restated or amended, as though a direct signatory thereto.

It contained a “jurisdiction” clause that stipulated Washington law as governing and the U.S. District Court for the Western District of Washington as the exclusive judicial forum:

Governing Law: Jurisdiction. This Grant Agreement and the transaction contemplated hereby shall be governed by and construed according to the laws of the state of Washington. With respect to any dispute arising out of or related to this Grant Agreement or the LLC Agreement, the parties hereby consent to the exclusive jurisdiction of the United States District Court for the Western District of Washington. . . .

yay-1916763-digitalThe LLC Agreement, unlike the Grant Agreement, contained a broad arbitration agreement, which said:

Arbitration. All disputes, claims or controversies relating to this Agreement that are not resolved by mediation shall be submitted to final and binding arbitration. . . . Questions or arbitrability or the scope of the parties’ agreement to arbitrate shall be determined by the arbitrator.

But like the Grant Agreement, the LLC Agreement also contained a jurisdiction and venue clause:

Jurisdiction and Venue. Any suit involving any dispute or matter arising under this Agreement may only be brought in the United States District Court for the Western District of Washington or the Superior Court of Pierce County. All Members hereby consent to the exercise of personal jurisdiction by any such court with respect to any such proceeding.

The LLC terminated the plaintiff on November 6, 2014, and on December 15, 2014 offered to buy plaintiff’s 10% interest out for $158,882.60. The plaintiff refused the offer one week later, claiming that he did not believe it to be accurately valued.

yay-13760132Unable to agree a resolution the plaintiff filed suit in March 2015, requesting a judgment declaring he has a 20% interest in the profits of the LLC, and equitable relief.

The LLC moved on April 3, 2015 to dismiss for improper venue or to stay the action pending arbitration under Section 3 of the Federal Arbitration Act pending arbitration. The Court denied the motion.

The District Court’s Analysis and Conclusions

The Court began its analysis by acknowledging that its “role” was confined “‘to determining (1) whether a valid agreement to arbitrate exists and, if it does, (2) whether the agreement encompasses the dispute at issue.’” Slip op. at 4 (quoting Chiron Corp. v. Ortho Diagnostic Sys., Inc., 207 F.3d 1126, 1130 (9th Cir. 2000)). If the arbitration proponent establishes that the answers to both questions are “yes,” then, said the Court, the Court must “‘enforce the arbitration in accordance with its terms.’” Slip op. at 4 (quoting 207 F.3d at 1130). And in discussing the standard applicable to question (2), the Court, playing homage to the strong presumption in favor of arbitration, said “‘any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration. . . .’” Slip op. at 4 (quoting 207 F.3d at 1131).

So far, so good. But having accurately stated the governing rules, the Court inexplicably failed to heed them. Continue Reading »