Re Colorado Energy Management, LLC v. Lea Power Partners, LLC: Another Appellate Division holds Construction Arbitration Award should be Vacated, but this time for Good Reason

May 10th, 2014 American Arbitration Association, Appellate Practice, Arbitrability, Arbitration Practice and Procedure, Arbitrator Vacancy, Authority of Arbitrators, Awards, Construction Industry Arbitration, Functus Officio, Grounds for Vacatur, Judicial Review of Arbitration Awards, New York State Courts, Practice and Procedure, State Arbitration Law, State Arbitration Statutes, State Courts Comments Off on Re Colorado Energy Management, LLC v. Lea Power Partners, LLC: Another Appellate Division holds Construction Arbitration Award should be Vacated, but this time for Good Reason

Introduction

In our recent post on the Merion Construction case (here), we were pretty critical of New Jersey’s Superior Court, Appellate Division, for reversing a trial court decision confirming a modified arbitration award, finding it should have been vacated and the original award confirmed. Today’s post takes a brief look at a decision by another state’s Appellate Division—New York’s Supreme Court, Appellate Division, First Department—which held that another construction-industry award should be vacated.

In Merion Construction the New Jersey Appellate Division thought the arbitrator had no authority to correct his award to reflect the rulings he intended to make on two issues the parties had submitted to him. Re Colorado Management, LLC v. Lea Power Partners, LLC , ___ A.D.3d ___, ___, 2014 N.Y. Slip Op. 01253 at 1-3 (1st Dep’t Feb. 20, 2014), held that a final arbitration award had to be vacated because the arbitrator had no authority to rule upon an issue that was not presented to him in light of the parties’ submissions and a ruling made in the same proceeding by a predecessor arbitrator.

While Merion Construction got an “F,” Colorado Management gets at least an “A-,” and perhaps even an “A.” Continue Reading »